Status Item | Current Status | Previous Status | Comment |
Schedule | yellow | yellow | |
Resources | green | green | |
Financials | yellow | yellow | Small variance of actual vs budgeted hours requirement review activities & build |
Quality | green | green | |
Project Issues | green | green |
Key Deliverables | % | Comments | Timeline |
Requirement Sign-off | 79% | In Progress | 12/14 |
Data Model/Mapping | 82% | In Progress | 1/12 |
Build | 63% | 50% Completed, 13% In Progress | 3/28 |
Integration | 0% | In Progress | 3/28 |
Training/UAT | 0% | Not Started | 4/1 |
For the detailed February 14, 2019 status report, click here.